Entire Description From 2008 to 2015 delay in construction


20th October 2008 : As per our talks with R.C.Construction Company for redevelopment of our Chawl Janta Nagar. R.C.Construction Company gave us a Cheque of Rs 1,80,000/- (One Lac Eighty Thousand Rupees)  towards Alternate Accommodation for the period of 18 months’ Rent @ Rs 10,000/- per month and requested us to find an alternate accommodation for ourselves.

As per our Agreement the R.C.Construction Company agreed to give us 400 Square Foot Carpet Area Plus he agreed to give us 50 Square Foot extra at Rupees 6000/- (six Thousand Only) per Square foot, for that R.C.Construction Company took 3 Cheques of Rupees 1,00,000/- (One Lac Only )  Each.  R.C.Construction Company has told us we have to clear the first cheque on construction of First Floor, Second Cheque on construction of Fifth Floor and the last cheque before he gives us the keys of my flat.

R.C.Construction Company said they have not included the 50 Square foot extra they are giving in the main agreement and they will give a Supplemental Agreement for the 50 Square Foot extra apart from the 400 Square Foot they will be giving.

29th July 2010 : I sent R.C.Construction Company a Reminder Notice demanding rent for Alternate Accomodation as per  R.C.Construction Company letter dated 28th December 2008. As 18 months had completed on 27th June 2010. 

30th july 2010 to 6th july 2012 : I had Called the Office of  R.C.Construction Company Several times only to Receive false assurances that the Building work is in progress and it will be completed soon.

07th July 2012 : I sent a Second Reminder Notice to R.C.Construction Company demanding Rent and Completing the Construction of Building a soon as possible as I had a major operation of Hernia and my last wish is to stay in my own house before my death but in Vein.

Year 2012 -2013 :  R.C.Construction Company Broke our Gallery and started the Construction of 8th and 9th Floor, I doubt that R.C.Construction Company broke our gallery and  used the FSI of our gallery for building 8th and 9th floor. When we asked for a reply R.C.Construction Company told us it broke our gallery as per order of the B.M.C. office. when we demanded a written permission or order they refused to show us. I assumed they were giving false information so i thought of filing an RTI against R.C.Construction Company.

28th October 2014 :  My son Shri Shyam Bahl filed a Request for RTI under the Right to Information Act 2005 for our Building which is under Redevelopment. But he could not get the information as the Builder and his goons threatened my son with dire consequences. The Builder even said that Kurla Police Station Officers are in his pocket and they won’t entertain any complaint related to R.C.Construction Company so I was afraid to file any complaint against R.C.Construction Company as I am old and I have a only one son and a daughter . I would like to mention R.C.Construction Company and their goons should be held responsible if anything happens to me, my son or any of my family members.